Roofing change order template
On a roof, the surprises are under the shingles, and they appear the day the tear-off happens — with the crew on the roof and the client away at work. This page covers what the change order must record so the decking, flashing and code work get approved instead of absorbed. The generator is free and needs no login.
No login, no email. The roofing template is preloaded and the PDF is yours to keep.
What a roofing change order must contain
These are the parts that decide whether the document settles an argument or starts one.
- The change, measured on the roof
- Six sheets of 7/16 OSB at the south eave, 96 linear feet of ice-and-water shield, step flashing at the chimney. Sheets and linear feet, not “decking repairs”, because a measured line is a line the client can accept or question.
- What the tear-off revealed, and when
- The roof was stripped on the 3rd and six sheets were soft at the eave. A dated finding, tied to the tear-off, is what makes the extra cost a condition of the building rather than a mistake by the roofer.
- Price per material and per unit of work
- Sheets, underlayment, flashing, ventilation, labour. Roofing changes are priced in units and installed in a hurry, so the change order should read like the material list.
- Code-required work triggered by the re-roof
- Many jurisdictions require an ice barrier, drip edge or added ventilation when a roof is replaced. When the contract did not include it, the change order is where the client sees that the requirement is the code's, not yours.
- The weather window and the schedule
- An open roof is a countdown. Say how many days the change adds and whether the roof will be dried in each night, because that is the client's real worry.
- Written approval with a date
- The signature can come by phone or email when the roof is open, but the price and the scope have to be on the document first.
The roofing traps that cost you money
- Decking found rotten after tear-off
- Soft sheathing, a delaminated sheet, a patch where a previous roofer nailed over a hole. You cannot shingle over it, and the client has never priced it. Photograph the sheet, count it, and get approval before the new material goes down.
- Code-required upgrades
- Ice-and-water shield at the eaves and valleys, drip edge, ridge venting that balances the intake. A re-roof often triggers these even when the original contract priced a single layer of felt.
- A second layer nobody mentioned
- The quote assumed one layer and there are two. Tear-off doubles, disposal doubles, and the decking underneath may be the original and in poor condition. This is the single most common way a roofing quote becomes a loss.
- Flashing that cannot be reused
- A chimney with no step flashing under the shingles, a skylight curb that has been patched twice, a wall intersection with no counter-flashing. Reusing it guarantees a callback; replacing it is scope the client has not seen.
- Insurance supplements
- Where a claim is paying, the adjuster approves a scope and the change order documents what falls outside it and who pays the difference. Keep the two documents separate so neither is used to argue against the other.
A filled-in roofing change order
Three line items, quantities, unit prices, markup and the total, with the reason written the way the homeowner needs to read it.
Change order
Sample Roofing
Sample document — illustrative figures
- Order
- CO-001
- Date
- Jun 2, 2026
- Client
- Homeowner — full tear-off, south slope
- Project
- 9 Quarry Hill
| Item | Qty | Unit price | Markup | Total |
|---|---|---|---|---|
| Remove and replace rotted roof sheathing, 7/16 OSB | 6 ea | $78.00 | 15% | $538.20 |
| Ice-and-water shield at eaves and valleys, code required | 96 lf | $6.50 | 10% | $686.40 |
| Replace step flashing at chimney, 24 lf, including counter-flashing | 24 lf | $18.00 | 10% | $475.20 |
- Subtotal
- $1,524.00
- Markup
- $175.80
- Total due
- $1,699.80
Reason for the change
The contract priced a single-layer tear-off over sound decking. After the south slope was stripped, six sheets of sheathing at the eave were soft and one had delaminated, so they cannot be shingled over. The chimney also had no step flashing under the shingles, only sealant, and the eave needs an ice-and-water shield that the original scope did not include.
Effect on schedule
Decking replacement adds one day. The south slope is dried in each night; the chimney flashing has to be complete before the ridge cap goes on.
Client signature
Printed name
Date
Contractor signature
Printed name
Date
When to issue one
- Tear-off reveals rotten or delaminated decking, or a second layer that the quote did not include.
- A re-roof triggers code-required ice barrier, drip edge or ventilation that the original scope left out.
- Flashing at a chimney, skylight or wall cannot be reused and has to be rebuilt rather than re-nailed.
- Storm damage found mid-job is beyond what the adjuster approved, and the difference needs to be documented separately from the claim.
Questions contractors ask
- Do code-required roof upgrades belong on a change order?
- Yes, when they were not in the signed scope. Requirements vary by jurisdiction, but where an inspection requires an ice barrier, drip edge or balanced ventilation, the cost is real work that was not priced. The change order shows the client it is a code requirement and gives them a number to approve.
- How does a change order work with a homeowner's insurance claim?
- Keep them separate. The claim covers the scope the adjuster approved; the change order records what was found during the work and was not in that scope, with a price and the client's approval. Mixing the two documents lets one be used to argue about the other.
- Is this roofing change order template free?
- It is free and needs no login. You fill it in, check the preview and download a PDF. Nothing you type leaves your browser, and the paid plans that add sending, e-signature and payment are not launched yet.
Put your name and price on it in two minutes
The generator opens with the roofing line items already in it. Edit them, add the reason, download the PDF, and hand it over before the work starts.
Other trade templates
- Electrical change order templateWhat it must contain, an example and the traps.
- Plumbing change order templateWhat it must contain, an example and the traps.
- Kitchen remodel change order templateWhat it must contain, an example and the traps.
- Bathroom remodel change order templateWhat it must contain, an example and the traps.
- Tile change order templateWhat it must contain, an example and the traps.
- Free change order generatorAll nine trade templates, line items, markup and a PDF.