Plumbing change order template

Plumbing work changes for two reasons: the client picks something different, or the wall comes open and the pipe behind it is not what anybody planned for. Both need a change order with a price and a date on it, or the difference comes out of your margin. The generator below is free, needs no login, and preloads a plumbing template you can edit.

No login, no email. The plumbing template is preloaded and the PDF is yours to keep.

What a plumbing change order must contain

These are the parts that decide whether the document settles an argument or starts one.

What the change is, in pipe and fixture terms
Relocate the tub drain and supply, replace the galvanised stub-outs at the lav, add quarter-turn shutoffs. Name the fixture and the location. “Plumbing modifications” tells the client nothing and gives them room to disagree about what they approved.
The reason, dated
The client selected a freestanding tub after the rough-in was priced; the floor came up and the subfloor was wet. Give the trigger and the day it was found. A dated reason is the difference between a documented change and a complaint about a bill.
Itemised labour and material
Each move, each stub-out, each valve on its own row with quantity, unit and unit price, with markup shown separately. Plumbers routinely absorb a fitting and a half hour and then wonder where the margin went; the change order is where that stops.
Access and restoration
Say what has to be opened — floor, wall, ceiling — and who puts it back. Tile, drywall and paint after a drain move are often more than the plumbing itself, and they are the first thing a client says they did not agree to pay for.
Permit and inspection impact
A moved rough-in usually means an amended permit and another inspection. State who pulls it, who pays the amendment, and which date moves if the inspection fails. If the work is behind a wall, say when the wall can close.
Signature, printed name and date
The client's written approval on the same page as the price. One screen or one sheet, not an email thread that says “sounds good”.

The plumbing traps that cost you money

What the pipe is actually made of
Cast iron with a split hub, galvanised supply that crumbles at the thread, polybutylene. Any of these can turn a fixture swap into a repipe, and none of them can be seen at signing. Price the consequence, not the surprise.
Code upgrades you inherit by touching the system
Replace a water heater and the discharge pipe, expansion tank and pan may all have to come up to current code. Alter a drain and the vent may no longer be legal. The client hears “you broke it”, the inspector hears “you touched it”, and the change order is where you say which is which.
Water damage that is not yours
Old staining on a joist, a soft subfloor under a pan, a slow leak that has been running for years. Photograph before you cut, describe the condition, and price the repair as a separate line so nobody assumes the leak started the day you arrived.
The fixture the client supplies
An owner-supplied faucet or tub with the wrong rough-in, missing trim or a discontinued cartridge is a schedule risk, not a plumbing fault. Say in the change order what you are installing, that it is supplied by the owner, and what the extra visit costs if it does not fit.

A filled-in plumbing change order

Three line items, quantities, unit prices, markup and the total, with the reason written the way the homeowner needs to read it.

Change order

Sample Plumbing & Heating

Sample document — illustrative figures

Order
CO-004
Date
Mar 3, 2026
Client
Homeowner — hall bath remodel
Project
88 Fulton Ave.
ItemQtyUnit priceTotal
Relocate tub drain and supply for freestanding tub: cut and fit ABS, new fittings, re-vent1 ea$640.00$736.00
Replace corroded galvanised stub-outs with PEX at lav2 ea$135.00$297.00
Install quarter-turn shutoff valves, lav and water closet2 ea$60.00$120.00
Subtotal
$1,030.00
Markup
$123.00
Total due
$1,153.00

Reason for the change

The contract priced an alcove tub on the existing drain. The owner selected a freestanding tub after demo, and the existing drain sits in the wrong place for it, so the drain and supply have to be moved and re-vented. The galvanised stub-outs at the lav were corroded and one broke off at the wall when the old cabinet came out.

Effect on schedule

Rough-in inspection needs to happen before the tile goes down. Tile moves two working days; the tub has to be on site before the drain is set.

Client signature

Printed name

Date

Contractor signature

Printed name

Date

Start from this template

When to issue one

  • The client changes fixture type, size or location after the rough-in has been priced.
  • Opening a floor, wall or ceiling shows pipe that has to be replaced before a legal connection can be made.
  • Touching one part of the system triggers a code upgrade — venting, a discharge pipe, an expansion tank, a shutoff that has to be accessible.
  • A repair turns into a repipe, or an owner-supplied fixture does not match the rough-in you priced.

Questions contractors ask

Who pays for the tile after a drain is moved?
Whoever the change order says. The safe answer is that the change order prices the plumbing, the tile repair and the waterproofing as separate line items, so the client sees the whole cost of moving the drain before they approve it. Leaving it out means you either eat the tile or argue about it later.
Is a text message from the client enough approval?
It is evidence, but it is weak evidence — no price, no scope, no date, and easy to characterise as a question rather than an approval. A change order with the price and a signature takes a minute and settles the argument in a way a message thread does not.
Does using this plumbing change order template cost anything?
No. The generator is free, requires no account and exports a PDF you keep. Nothing you type is sent anywhere; the sending, e-signature and payment features are part of the paid plans and are not launched yet.

Put your name and price on it in two minutes

The generator opens with the plumbing line items already in it. Edit them, add the reason, download the PDF, and hand it over before the work starts.