Electrical change order template

An electrical change order is the document that turns a verbal yes on site into an approved circuit, an approved price and an approved date. This page shows the fields that survive an argument at final invoice, plus a worked example you can copy the shape of. The generator is free and needs no login — pick Electrical, edit the line items and download the PDF.

No login, no email. The electrical template is preloaded and the PDF is yours to keep.

What a electrical change order must contain

These are the parts that decide whether the document settles an argument or starts one.

The change, in devices and locations
Name the work the way you would order it: a 20A dedicated circuit for the island receptacles, six 4 in. recessed lights over the sink run, a new dimmer at the entry. “Electrical extras” is not a description — it is an opening for the client to argue about which extras they meant.
Why it changed, and who asked
Owner request during rough-in, a correction notice from the inspector, or a wall that came open and showed something the contract never assumed. State the trigger and the date it came up, because that is what separates an approved change from a cost overrun.
A line-item price breakdown
Each circuit, fixture, hour and patch as its own row with a quantity, a unit and a unit price, then your markup on top. One lump sum invites a counter-offer on the whole number; itemised rows invite a question about one row, which is a much cheaper conversation.
The effect on the schedule
Electrical rough-in sits in front of insulation, inspection and drywall. If the added circuit has to be inspected before the walls close, say which date moves and by how many working days. A change order that quietly slips the schedule is the one that costs you the relationship.
The client's written approval, with a date
Printed name, signature, date. The date is not decoration: it fixes when the price was agreed and when the clock on the extra work started. Without it, the conversation at final invoice becomes a memory test.
A reference to the original contract
One line saying this change order amends the signed scope of work and that the rest of the contract stands. That sentence is what makes the document an amendment rather than a suggestion.

The electrical traps that cost you money

Concealed conditions
Knob-and-tube, aluminium branch wiring, an ungrounded circuit, a junction box buried behind the drywall. None of it is visible at contract signing, all of it appears at demo, and none of it was in the client's budget. Photograph it, describe it in the change order, price it before you touch it.
Permit-driven changes
An inspector who wants AFCI protection, a dedicated circuit for a new appliance, or a box relocated out of a wet location has just added scope that nobody asked you for. Say that the work is inspection-driven, name the correction, and price the re-inspection if a second visit is required.
Panel capacity
The panel may have no spare spaces, or no capacity for one more 20A circuit. If the honest answer is a subpanel or a service upgrade, put that in the change order before you buy the breaker — the number is far bigger than the client expects and far better heard now than at handover.
Who repairs the wall
Cutting for a new circuit means drywall, paint and sometimes texture that nobody has priced. Either include the patch and paint as a line item or state in writing that the client is arranging it. Silence here becomes your cost.

A filled-in electrical change order

Three line items, quantities, unit prices, markup and the total, with the reason written the way the homeowner needs to read it.

Change order

Sample Electric Co.

Sample document — illustrative figures

Order
CO-002
Date
Feb 11, 2026
Client
Homeowner — kitchen remodel
Project
412 Maple St.
ItemQtyUnit priceTotal
Add 20A dedicated circuit for island receptacles: home run to panel, new AFCI breaker1 ea$385.00$442.75
Install 4 in. recessed LED downlight, new construction, including trim6 ea$95.00$627.00
Cut and patch drywall at light locations, ready for paint6 ea$45.00$270.00
Subtotal
$1,225.00
Markup
$114.75
Total due
$1,339.75

Reason for the change

During rough-in the homeowner asked for receptacles on both sides of the new island and for six recessed lights over the sink run and the island. None of that was in the signed scope, and the island receptacles need their own 20A circuit with a home run to the panel. The panel had one spare space, so no subpanel is needed.

Effect on schedule

This work has to be complete and inspected before the drywall date. Drywall moves one working day to allow for the inspection.

Client signature

Printed name

Date

Contractor signature

Printed name

Date

Start from this template

When to issue one

  • The homeowner adds outlets, fixtures or a circuit after rough-in has been priced and approved.
  • Demo opens a wall and the wiring inside is not what the contract assumed — no ground, undersized conductors, or a panel with no room left.
  • An inspector's correction notice requires work outside the signed scope, such as a dedicated circuit or a relocated box.
  • The added load needs a subpanel or service upgrade, and the client needs to approve that number before anything is ordered.

Questions contractors ask

Does an electrical change order need to be notarised?
No. What matters for a residential remodel is that the client signed it, that the date is on the document, and that the scope and the price are unambiguous. A notary adds ceremony, not clarity, and it is not something you should feel obliged to arrange.
Can I write a change order after the electrical work is already done?
You can, but you have given away the leverage that makes it easy to collect. The document exists to get approval before the work starts. If the work is already in, issue it the same day and note when the change was authorised verbally, so the client is confirming a decision rather than meeting a surprise invoice.
How much does this electrical change order template cost to use?
Nothing. The generator is free, needs no login and no email, and exports a real PDF you can print or send. Your entries stay in your own browser — the paid plans, which add sending, e-signature and payment collection, are not launched yet.

Put your name and price on it in two minutes

The generator opens with the electrical line items already in it. Edit them, add the reason, download the PDF, and hand it over before the work starts.

Other trade templates